Tuesday 23 March 2010

The digger moves in


The demolition is still underway and the digger has now gone to work. Here are the latest pictures.








Thursday 18 March 2010

A bit more demolition


Just a few more pics of the demolition in progress. Slow but sure.




Wednesday 17 March 2010

Raising the Roof

Demolition proper started today, the tiles are coming off and the floor boards and joists are disappearing.

The neighbours telephone cable will be relocated on Monday as it drapes very low across our property - more expense, but BT have you over a barrel.

Getting there!















Saturday 13 March 2010

Not a lot has happened this week on site, but in the background we have got a few things moving. Firstly Kevin the architect is now drawing up the amended plans which will then go to the structural engineers so that they can re calculate the steels, then be submitted to the planning office for approval.
We also decided to save one of the trees in the garden as it is pretty in summer and does not block the view.
Demolition should recommence this Wednesday all being well.
We have also agreed the electrical lighting plan and have the air exchange unit being looked into.
So it's all steam ahead.









Tuesday 9 March 2010

Brilliant News

We have been told that if we put in for amended planning permission our Planning Officer will look on it favourably. This means that the metre that he knocked off the back of our property can now be put back in glass with amended planning permission. Long story, but the outcome is we get what we want. Fingers crossed this goes as planned. Just a couple of things to do now, get the new amended plans drawn up, seeing Kevin our architect at 11am tomorrow then we have to see Bob who drew up the structural plans to get the steel work re-jigged, hopefully it can be done as the wall that supports the largest metal beam has to be relocated.

Wednesday 3 March 2010

Demolition stops

Everything was going so well, a bit too well apparently.

The demolition team were only supposed to be removing the asbestos but over-stepped the mark by starting the full demolition.
Demolition can be re-started on the 19th March when all the correct demolition notices have been served upon our neighbours as required by 'The Party Wall Act' and by law.
So it's not a step back we are going in the right direction, we just have to proceed at the correct speed.

Monday 1 March 2010

The site gets fenced off

The site has now been fenced and the demolition is under way. Woo hoo.