Thursday, 27 January 2011

The doors arrive


The Balconette team led by Peter arrived on site on Monday and by Tuesday evening the doors were in.
We are very pleased with the doors and panels and when the glass roof is fitted at the end of February along with the glass balustrade the whole back will be tied together and in our opinion look the bees knees.
The doors took 4 months in total to manufacture and arrive from Israel and as they are bespoke we are so relieved that they fit perfectly. Another 4 months in production would have been unthinkable.
A brilliant day on site.


















Tuesday, 18 January 2011

Odd pictures from today


A few photos taken on site and in the park today.
We now have a step to get out onto the balcony.
The outside walls have had their first coat of K-Rend, this will be finished off tomorrow, thank goodness for good weather. By the way, the colour tones down, it isn't egg yolk yellow really.
The plasterers are still on site and still dry lining the downstairs walls.
The window fitters have been in fixing bits and pieces, still awaiting some windows, first ones delivered were the wrong size.





















































Saturday, 15 January 2011

Quick catch up

We are now well into January and things are progressing now that the harsh winter weather appears to be behind us.

I have added a few random pictures to show the work in progress.

Today the plasterers are working on the ground floor walls having completed the upstairs plastering.

The stairs have gone in, but obviously not finished, trying to keep them looking good until the build is complete.

We have underfloor heating in the bathrooms and work is progressing with the plumbing.

We have a few more windows including the large master bedroom window and the view is still brilliant.