It was all hands on deck today.

The plumbers were putting pipes in the kitchen and utility room and the floor preparation was underway.

Celetex insulation is going down on the block and beam floor and that will be followed by the underfloor heating next week.

On Wednesday (subject to weather) 3" of cement and floor screed will be applied to all the ground floor.

The floor should dry out over Christmas so work should not be interrupted on return in January.

The window fitters were on site as well. They are fitting the first floor windows at the front.

Things are taking shape and we hope the weather holds and the snow and ice stay away.