Thursday, 27 January 2011

The doors arrive


The Balconette team led by Peter arrived on site on Monday and by Tuesday evening the doors were in.
We are very pleased with the doors and panels and when the glass roof is fitted at the end of February along with the glass balustrade the whole back will be tied together and in our opinion look the bees knees.
The doors took 4 months in total to manufacture and arrive from Israel and as they are bespoke we are so relieved that they fit perfectly. Another 4 months in production would have been unthinkable.
A brilliant day on site.


















Tuesday, 18 January 2011

Odd pictures from today


A few photos taken on site and in the park today.
We now have a step to get out onto the balcony.
The outside walls have had their first coat of K-Rend, this will be finished off tomorrow, thank goodness for good weather. By the way, the colour tones down, it isn't egg yolk yellow really.
The plasterers are still on site and still dry lining the downstairs walls.
The window fitters have been in fixing bits and pieces, still awaiting some windows, first ones delivered were the wrong size.





















































Saturday, 15 January 2011

Quick catch up

We are now well into January and things are progressing now that the harsh winter weather appears to be behind us.

I have added a few random pictures to show the work in progress.

Today the plasterers are working on the ground floor walls having completed the upstairs plastering.

The stairs have gone in, but obviously not finished, trying to keep them looking good until the build is complete.

We have underfloor heating in the bathrooms and work is progressing with the plumbing.

We have a few more windows including the large master bedroom window and the view is still brilliant.






































Monday, 27 December 2010

We have a floor


The ground floor under floor heating has been installed and the concrete floor laid over the top.
The floor should be dry when the workforce returns after the Christmas Holiday.
Then all steam ahead.




Friday, 17 December 2010

We have windows

It was all hands on deck today.

The plumbers were putting pipes in the kitchen and utility room and the floor preparation was underway.

Celetex insulation is going down on the block and beam floor and that will be followed by the underfloor heating next week.

On Wednesday (subject to weather) 3" of cement and floor screed will be applied to all the ground floor.

The floor should dry out over Christmas so work should not be interrupted on return in January.

The window fitters were on site as well. They are fitting the first floor windows at the front.

Things are taking shape and we hope the weather holds and the snow and ice stay away.









Wednesday, 15 December 2010

Plastering







The upstairs is being plastered and should be finished tomorrow.
The downstairs floor is being prepared for underfloor heating and the new floor should be laid next week and will hopefully be drying out over Christmas.



Tuesday, 14 December 2010

Big freeze halts build

Progress has been a bit slow on site as sub zero temperatures halted the plastering, frozen pipes and freezing temperatures stopped the plasterers working. The chippies have been heros, only missing 2 days.

Well now the plastering is underway and the side roof has been completed.

We have moved houses and all appears to be going well in that department.

I will attempt to get some photos uploaded this week.