Monday 29 November 2010

K-rend and plastering


Just a few pics to show the exterior K-Rend on the side wall and pics to show that the plastering has actually started.
The plastering will be stopping tomorrow as it is too cold unless the builders can come up with some good heaters.
The build schedule will be falling behind again as everything is now subject to the weather, which is freezing, especially on the coast.














Thursday 25 November 2010

It's getting cold


It was certainly cold on site today and the carpenters really felt it as they are working on the side roof. There are no rear windows yet, so the whole site is like a deep freeze.

Holmans have completed the first fix on the data cabling, as you can see from the photo we have a few cables, well actually we have loads of cables, it is amazing.

Most of the upstairs has been plaster boarded and the plasterer should be plastering tomorrow.

The electrician has almost finished the first fix as well.

We are now awaiting the chap to do the K-rendering to the side wall so that the roof can go on. This looks like it may hold the whole job up and we need to get it done so that the floor can go down before Christmas, this would give it a good chance to dry over the Christmas period.














Sunday 14 November 2010

Plasterboard going up


Just a few pics of the first floor, you can see the plasterboard has started to go up and you can also just make out the ducting for the air handling system.
Pipes and wires everywhere.
Things are starting to take shape.
Holmans in Wimborne have been brilliant. They have sorted out our sound system and speakers and also our data points throughout the house, we would highly recommend them.













Saturday 6 November 2010

Odd pics, in no particular order


The front of the house.




Andy's bedroom

Pipework under en-suite floor.



Inside the roof on the balcony.





Looking through the lounge to the park beyond.






same again.





Steps from garden which lead up to the curved glass patio doors.










Looking up at more plumbing and the air handling ducting in the utility room.
















The back of the house, big steps.
























Steps again.
















The curved beam over the patio doors looking up to the balcony.











The back of the house from the garden.






Friday 5 November 2010

All trades on site


Only two photos, sorry, I will take some more over the weekend when the site is empty and the light is better.
Well now for the update, all trades have been on site this week, we have had
Allergy Plus installing the ducting for the Air Handling System.
Paul and team installing the Solar Panel bits, plumbing and underfloor heating for the bathrooms.
Steve the electrician running wires all over the place for the lighting circuits up stairs.
Brickies constructing the outside steps and doing fiddly brick bits above the first floor front windows.
The tilers have been back to put on the ridge tiles.
The chippies have finished the stud work for the upstairs and are now inserting really thick insulation, talk about toasty, it is really thick.
Brian and I have sorted out the mirrors for the bathrooms and have found just the right lights for the bedrooms, collecting tomorrow.
The site office has been taken away to allow more room at the front so that the footings for the front walls can start, probably a few weeks away, but it is a start.
All the windows are now on order and hopefully they will arrive before the chippies freeze to death, the wind can be very cruel straight off the sea and the plastic sheeting has a few holes appearing in it.
Excellent progress this week, long may it last.