Friday 5 November 2010

All trades on site


Only two photos, sorry, I will take some more over the weekend when the site is empty and the light is better.
Well now for the update, all trades have been on site this week, we have had
Allergy Plus installing the ducting for the Air Handling System.
Paul and team installing the Solar Panel bits, plumbing and underfloor heating for the bathrooms.
Steve the electrician running wires all over the place for the lighting circuits up stairs.
Brickies constructing the outside steps and doing fiddly brick bits above the first floor front windows.
The tilers have been back to put on the ridge tiles.
The chippies have finished the stud work for the upstairs and are now inserting really thick insulation, talk about toasty, it is really thick.
Brian and I have sorted out the mirrors for the bathrooms and have found just the right lights for the bedrooms, collecting tomorrow.
The site office has been taken away to allow more room at the front so that the footings for the front walls can start, probably a few weeks away, but it is a start.
All the windows are now on order and hopefully they will arrive before the chippies freeze to death, the wind can be very cruel straight off the sea and the plastic sheeting has a few holes appearing in it.
Excellent progress this week, long may it last.

No comments:

Post a Comment