Thursday 25 November 2010

It's getting cold


It was certainly cold on site today and the carpenters really felt it as they are working on the side roof. There are no rear windows yet, so the whole site is like a deep freeze.

Holmans have completed the first fix on the data cabling, as you can see from the photo we have a few cables, well actually we have loads of cables, it is amazing.

Most of the upstairs has been plaster boarded and the plasterer should be plastering tomorrow.

The electrician has almost finished the first fix as well.

We are now awaiting the chap to do the K-rendering to the side wall so that the roof can go on. This looks like it may hold the whole job up and we need to get it done so that the floor can go down before Christmas, this would give it a good chance to dry over the Christmas period.














No comments:

Post a Comment